Project |
School Priority |
AMP priority |
Est Gross £ |
Source of Funding |
Timing |
Comment |
|
Refurbish toilets |
high |
medium |
£20,000 |
School Formula |
has to be summer holidays |
health and safety issue |
|
replace old mobiles |
medium |
high |
£190,000 |
bid to LCVAP |
6 – 8 month contract |
We will lose some playground which must be replaced Need to fundraise for 10% |
|
replace roof |
Medium |
high |
£100,000 |
bid to LCVAP |
Has to be summer holiday |
AMP says high priority, but consultant says it will go another year or two with some patching |
|
develop proper nursery play area |
high |
not mentioned |
£20,000 |
school formula plus parents fund, or could try LCVAP bid or seed challenge |
can be anytime |
lack of this facility noted in OFSTED report |