Project Milestones

What are the Key Project Milestones?
  • Task Finish Project Scoping and obtain funding 19/06/96 - completed
  • Set up committees and workers 01/10/96 - completed
  • Write PID 01/12/96 - completed
  • Write Other specifications 01/03/97 - completed
  • Internet feed to first secondary school 01/03/97 - completed
  • Internet feed to first primary school 01/09/97
  • Connect other secondary schools 01/08/97
  • Secondary Internet access commissioned 01/09/97
  • Install Digital Library TBD
  • Primary access to LEN 01/04/97
  • E-mail and Conferencing 01/09/98
  • Herts Career Services 01/09/99
  • Herts Library Service 01/06/97
  • Training 01/09/98

How Far Have We Got?

  • PID and Technical Specification issued
  • Project Board, Technical Committee and Curriculum Team meetings held
  • PC’s bought and installed in homes
  • Internet accounts obtained from CableOnline
  • Curriculum group researchers 10 hour Internet training complete
  • Internet subject research started
  • Technology for primary schools determined and first primary PC’s ordered.
  • All secondary school LAN's connected
  • Multimedia PC, printer and Internet capability insalled in all primary schools
  • All primary schools connected where CableTel infrastructure allows
  • E-mail available to all connected schools
  • Digital library research started
  • Lessons are being conducted using Internet access
  • Primary training started
  • First wave of secondary staff training complete, second wave started
LCET Home Page Start of "Letchworth Education Network"